How to Create a Change Order in Sedona

This is a quick guide to walk you through the steps on how to import a change order to Sedona.

From within the Sedona Office application, expand the Job Management category. From within that interface, select the Job Queue

Locate the Job by searching the job's number into the field

Double click to open the job

Go to Tasks and click on the first one. Select "Sequence Locks Job" and click save and than hit apply.

Right click on the task and click "Approve Task"

Go to Tools on the left-hand side and click on Add Change Order

Click on "WeSuite C/O" and click on Select on the pop up window

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

0 comments

Please sign in to leave a comment.