How to Configure 'Use Current Date for Won Job'

This is a quick guide to show you how to set up "Use Current Date For Won Job" instead of having the job's created date

There is a setting in Tools -> Program Options, that will allow you to change turn this feature On/Off. 

When set to 'False', the system will take the date specified in the Status Tab as the date that the job is won. 

When set to 'True', the Won Date will be the date when the status is changed.

To change this setting

1. Tools

2. Program Options

3. Program Options

4. Use Current Date for Won Job

5. Set to "True"